
Major Activities of the Month
The PI consultant team members’ assignment during the month of November was rather sparce compared with that of the previous month. Major activities of the PI consultant team during the reporting month are summarised below:
1. Steel Re-rolling Mill Energy Advisory Visit
On 3rd of November, the PI Consultant Team, with the attendance of SREDA officials, conducted an energy advisory visit to one of the mid-large scale steel re-rolling mills in Bangladesh using induction furnaces for its foundry. It was the third steel re-rolling mill to be visited by the PI Consultant Team after the steel mill with the latest arc furnace model (November 2019), and one of the largest induction furnace mill (March 2022). Its direct rolling process was one of the most striking energy efficient features to be observed.
An introductory presentation was given by the Project Director, followed by a walk-through inspection. Common practice for energy audits is, to share and collect a questionnaire / EE&C performance check sheet with the operating entity in advance, so that the audit team can make a preliminary analysis of the basic operational information, such as energy consumption and energy intensity and already implemented energy conservation measures.

Item | Information |
---|---|
■ Company name | |
■ Factory name | |
■ Address of factory | |
■ Contact person name & e-mail address | |
■ Starting year of operation | |
■ Product name | |
■ Production capacity (ton/year) | |
■ Production amount in 2021 (ton/year) | |
■ Number of engineers | |
■ Number of employees |

No. | Energy | Annual consumption |
---|---|---|
1 | Electricity from grid | kWh |
2 | Natural gas for production | m3 |
3 | Natural gas for captive power generation | m3 |
4 | LPG | kg |
5 | Fuel oil | Litre |
6 | Diesel oil | Litre |
7 | Other fuel, Oxygen | kg, L |
8 | Captive power generation | kWh |
9 | Contract demand of electricity | KVA |
However, in this case obtaining the required information in advance was not possible, so the focus was set on the on-sight survey. The steel re-rolling mill visited had already implemented two major energy conservation measures. One is the application of the steel billet direct rolling process. The natural gas consumption savings through the application of this technology for the steel re-rolling mill, based on estimated data, is as follows:

Assumption:
1) Annual steel bar production = 100,000 ton/y,
2) Direct rolling ratio = 40%
3) Fuel intensity of reheating furnace = 400 Mcal/ton
4) Natural gas heat value = 8,500 kcal/m3
Calculation:
Annual natural gas saving volume = 100,000 * 0.4 * 400,000 / 8,500 = 1,882, 000 m3/y

The second EE&C measure is the installation of inverter-controlled dust collector fans. The steel re-rolling mill operates a dust collector with an inverter-controlled fan motor to improve the working condition of its induction furnace and to save power consumption. As shown in the figure below, power consumption of a 100kW dust collector fan motor can be saved by up to 32kW through inverter-controlling.


Nevertheless, there were still several opportunities to further improve the plant’s energy performance. One major example was the reheating furnace. The furnace is operated by a manual valve control for natural gas and combustion air. Following recommendations were made by the audit team.
- Installation of an automatic combustion control system, to keep heat pattern of furnace stable. Automatic combustion control has the advantage, that it can control the flowrate of natural gas and combustion air to keep a low air ratio. It can also control the temperature and heat pattern in the furnace.
- Installation of a regenerative burner. The installation of a regenerative burner would require a huge renovation of the plant, but it would improve the energy efficiency drastically by utilising the exhaust heat.




Another recommendation was the improvement of the reheating furnace’s insulation. As shown in the thermal image above, the refractories of the side wall are showing a temperature of 68.2 degrees centigrade, which is reasonable. Meanwhile, the insulation material of the inspection doors is showing temperatures of 100.5 and 126.3 degrees centigrade. This is a sign, that the insulation material of the inspection doors needs to be replaced.
For the long-term scope, the audit team recommended the installation of ECOARC for induction furnaces. The steel re-rolling mill produces molten steel by using 2 20 ton/charge and 1 15 ton/charge induction furnaces. The installation of an electric arc furnace with scrap preheater, would have a huge power saving potential.

Equipment | Power intensity |
---|---|
Induction Furnace | 610 – 620 kWh/ton |
Electric Arc Furnace with Scrap Steel Preheater | 250 – 350 kWh/ton |

2. Compilation of the Golden Procedure of Building Energy Audit Documents
On 17th of November, Dr Kimio Yoshida, the EE&C promotion policy and technology expert of the PI Consultant Team, made a comprehensive presentation on the Golden Procedure of Building Energy Audit. The presentation was the comprehensive compilation of the fragmented findings and recommendations which were presented on many occasions in the past.
The focus was on the basic knowledge on building energy consumption features by building type which should be recognized among the auditors, before conducting the field visits. The most important among the preparation is to collect the following data.



Requirements are not only data collection, but also before conducting the field survey, expected output and potential recommendation should be imaged based on preliminary collected data and knowledge platform. The measuring equipment should also be chosen so that visualization of the imaged output will be possible. The template of standard building audit report should also be identified before the field survey.
Information collected from the actual field survey is also used as essential findings. The examples below are the findings on the absence of proper insulation in the case of some buildings in Bangladesh. Visualization using thermo-camera is quite effective and persuasive for to be included in the report.



3. Zero Energy Buildings Promotion
Also on 17th November, Dr Kimio Yoshida also presented the key points of Japan’s Zero Energy Building (ZEB) guidelines to SREDA. The presentation focused on a striking trend of the very rapid pace of ZEB and ZEH (Zero Energy House) penetration in Japan. The following elements were pointed out the major reasons why ZEB/ ZEH are increasing:

- Government had set the target to accelerate ZEB/ ZEH,
- To realize this target, the Government formulated comprehensive supporting mechanisms including the introduction of certification for ZEB planners and ZEH planners/ builders. As of end of October 2022, around 400 ZEB planners and around 3,700 ZEH planners/ builders have been certified. It is through these planners that the end users are given easy access to ZEB and ZEH.
- The Government has also published several ZEB guidelines and design tools, such as for mid-size office, small size office, hospital, hotel, school, nursery. Guidelines are also available for ZEH,
- The official ZEB/ZEH logos are becoming the status for the home and building owners, contributing to the awareness raising,
- Financial incentive mechanism for ZEB/ ZEH construction involving the central government, local municipality, and the financial institutions has been introduced.
4. Facilitating the Project Loan Utilisation
4.1 Observing the Issuance of NOCs and MIS Registration
As of the end of November, there were 15 NOCs issued during the months of September – October – November but were not registered on the Project MIS. The PI consultant team consulted with the SREDA PIU to confirm that the NOCs have been issued following requires steps and supported the PIU to catch up with the MIS record keeping. The following NOCs are now uploaded onto the Project MIS with an updated work record of the eligibility checking.

ID | Issue date | Sector | Equipment |
---|---|---|---|
AD22082301 | 29 Sep 2022 | Pharmaceutical | Compressor, chiller, LED, elevator |
AF22082101 | 24 Oct 2022 | Spinning | Gas engine for cogeneration |
AF22082102 | 24 Oct 2022 | Spinning | Gas engine for cogeneration |
AF22082103 | 24 Oct 2022 | Weaving | Gas engine for cogeneration |
AF22082104* | 24 Oct 2022 | Textiles | Gas engine for cogeneration |
AF22082105 | 24 Oct 2022 | Textiles | Gas engine for cogeneration |
AF22082106 | 24 Oct 2022 | Textiles | Gas engine for cogeneration |
AF22082107 | 24 Oct 2022 | Textiles | Gas engine for cogeneration |
AF22090201 | 24 Oct 2022 | Spinning | Gas engine for cogeneration |
AF22090202 | 24 Oct 2022 | Spinning | Gas engine for cogeneration |
AF22090203 | 24 Oct 2022 | Textiles | Gas engine for cogeneration |
AF22090204 | 24 Oct 2022 | Spinning | Gas engine for cogeneration |
AF22090205 | 24 Oct 2022 | Spinning | Gas engine for cogeneration |
AF22091901* | 03 Nov 2022 | Textiles | Sewing machine |
AD22091401 | 07 Nov 2022 | Cement | Gas engine for cogeneration |
(Note: AF22082104 and AF22091901 are awaiting manager approval.)

4.2 Project MIS Improvement
The Project MIS was found be in requirement for technical update in that the latest file encryption is not being accepted, resulting in difficulty to upload the scanned NOCs. CSL Software Resources conducted a minor maintenance to have this function updated. It was on this occasion that the list of the PI Consultant Team’s members who are involved in the issue management of the Project MIS was also updated.
5. Appendices
Appendix 39-1: Zahir Steel & Re-Rolling Mills Limited – Energy Advisory Visit Report
Appendix 39-2: Golden Procedure of Building Energy Audit – Hints for Bangladesh
Appendix 39-3: Introduction for the ZEB Guidelines in Japan