1. Activities and Achievements
1.1 Summary of Progress
- First on-site energy model audit conducted.
- Project data on MIS is being updated (ongoing).
- Discussion on scope enhancement started.
- Organised 15th Project Coordination Committee Meeting.


2. Appendices
Appendix 01-1: Three-Stages Strategy
Appendix 01-2: Implementation & Resources Allocation Plan for FY 2019-2020
Appendix 01-3: MIS Data Updating Requirements
Appendix 01-4: Eligible EEC Technologies – Target Sectors
Appendix 01-5: On-site inspection and survey of a spinning mill
Appendix 01-6: PCC15 Meeting materials and Record