achievements

Project Achievements in Figures

As of December 2022
As of December 2022

Sub-projects

There are 43 sub-projects which are using the preferential finance facility under EECPFP. The borrowers (=sub-project owners) range from textile, cement, building, electronics to total of 11 business sectors.

No.IDNOCSectorLoan amount 
(BDT million)
1SD170412012017/05/24Cement1,270
2SF151003012017/08/24RMG753.7
3SF170831012017/12/13Spinning253.95
4SF171030012018/06/10Spinning517.3
5SF170419012018/06/21Electronics10.51
6SD180625012018/06/28RMG109.03
7SD170503012018/09/13Cement734
8SD180701012018/10/03Spinning85.53
9SF180809012018/10/28Spinning116.54
10SD190404012019/10/03RMG805.43
11SF190521012019/10/03Spinning368.41
12AF190925012019/11/26Cement998.21
13SD190731012019/12/01RMG1000.00
14SF191224012020/01/13Weaving1000.00
15SD200323012020/08/13Spinnning1500.40
16AD191203012020/08/13RMG492.81
17SD191022012020/11/12Building922.92
18SD210518012021/10/28Electricity & heat302.87
19SF211003012021/10/31Spinning265.04
20AD211004012021/10/31RMG175.47
21SD211101012022/01/27Spinning414.27
22SD211221012022/03/29Cement1,546.69
23AF220512012022/06/13Spinning1,500.00
24AF220612012022/07/07Spinning1,139.14
25SD210314012022/08/08Education751.35
26AD220823012022/09/29Pharmaceutical 483.18
27AF220821012022/10/24Spinning 270.75
28AF220821022022/10/24Spinning 270.75
29AF220821032022/10/24Weaving 180.50
30AF220821042022/10/24Textiles 180.50
31AF220821052022/10/24Textiles 135.38
32AF220821062022/10/24Textiles 90.25
33AF220821072022/10/24Textiles 45.13
34AF220902012022/10/24Spinning 180.50
35AF220902022022/10/24Spinning 270.75
36AF220902032022/10/24Textiles 270.75
37AF220902042022/10/24Spinning 90.25
38AF220902052022/10/24Spinning 270.75
39AF220919012022/11/03Textiles119.35
40SD220914012022/11/07Cement 265.11
41AD221018012022/11/29Accommodation 776.17
42AF221009012022/12/22Cement 260.14
43AD221114012022/12/22Glass 671.24
TOTAL21,865
(As of December 2022)

Sector

Proportion and Sub-project Loan Amount per Sub-sector (as of December 2022)
Number of Sub-sector wise Proponents and Average Loan Amount per Sub-project
(as of December 2022)

Equipment

Proportion of EE&C Equipment Funded by the Project Fund (as of December 2022)

Energy Saving Effects

IDSectorEquipmentEnergy
saving
potential
(toe/yr)
Monetary
value
(BDT
million
/ yr)
Emissions
reduction
(t-CO2)
SD17041201CementVertical Roller grinding mill3,504 1018,295
SF15100301GarmentSewing machine, Air compressor, Air conditioner, LED light 1,355393,207
SF17083101SpinningRoving frame, Automatic winder, Ring spinning frame, Absorption chiller761221,237
SF17103001SpinningAir-jet spinning, Roving frame, Automatic winder, Absorption chiller887261,441
SF17041901ElectronicsAir compressor230.755
SD18062501GarmentSewing machine, Boiler, BEMS708201,666
SD17050301CementVertical roller grinding mill3,235937,658
SD18070101Textiles Gas engine cogeneration, LED light1,058302,170
SF18080901SpinningAutomatic winder471112
SD19040401GarmentSewing machine, Air compressor, Boiler791231,871
SF19052101SpinningAutomatic winder2678434
AF1909250 CementVertical roller grinding mill6,31718214,954
SD19073101GarmentSewing machine, air compressor, air conditioner, once through boiler, elevator, LED light 1,659484,178
SF19122401WeavingWeaving machine (loom)2,800814,551
SD20032301SpinningRoving frame, Automatic winder, Ring spinning frame, Absorption chiller5,0941478,581
AD19120301GarmentSewing machine, air compressor, absorption chiller, once through boiler, elevator, BEMS 1,189342,117
SD19102201Real estateHeat reflective glass, centrifugal chiller, elevator, water-cooled chiller 1,407413,330
SD21051801Electricity & heating Gas engine cogeneration with exhaust gas boiler8,18723619,198
SF21100301SpinningRoving frame, Ring spinning frame, Automatic winder, Gas engine cogeneration 815231,784
AD21100401GarmentSewing machine, air compressor, VRF, elevator 1956463
SD21110101SpinningRoving frame, Automatic winder, Gas engine cogeneration 11,04331821,269
SD21122101CementVertical Roller grinding mill, Air compressor8,01223118,968
AF22051201SpinningRoving frame, Automatic winder, Ring spinning frame, Gas engine generator with WHR Absorption chiller5,784 16711,465
AF22061201SpinningRing spinning frame, Multi Air Compressor with control unit, Gas engine generator with WHR Absorption chiller5,851 1681,551 
SD21031401EducationWater-cooled chiller, LED light, Heat reflective glass, Elevator 4,0541179,597
AD22082301PharmaceuticalAir Compressor, Water-cooled chiller, LED light, Elevator 905262,141
AF22082101SpinningGas engine cogeneration3,5211018,257
AF22082102SpinningGas engine cogeneration3,5211018,257
AF22082103WeavingGas engine cogeneration2,347685,505
AF22082104TextilesGas engine cogeneration2,347685,505
AF22082105TextilesGas engine cogeneration1,761514,128
AF22082106TextilesGas engine cogeneration1,174342,752
AF22082107TextilesGas engine cogeneration587171,376
AF22090201SpinningGas engine cogeneration2,347 685,505
AF22090202SpinningGas engine cogeneration3,5211018,257
AF22090203TextilesGas engine cogeneration3,5211018,257
AF22090204SpinningGas engine cogeneration1,174342,752
AF22090205SpinningGas engine cogeneration3,5211018,257
AF22091901TextilesSewing machines
SD22091401CementGas engine cogeneration3,39298 7,954
SD22101801AccommodationAmorphous core transformer, Water cooled chiller, Heat reflective glass, Elevator 3,9601149,376
AF22100901CementGas engine cogeneration6,79819615,691
SD22111401GlassAir compressor (centrifugal and screw), Gas engine cogeneration 5,83816811,983
As of December 2022

Energy Audit

  • Sub-projects energy audit conducted (as of March 2022) are as follows:

1. Aman Spinning Mills Limited.
2. Bandhab Tex Limited. (x2 times)
3. Asia Composite Mills Limited. 
4. Fair Electronics Limited.
5. Tosrifa Industries Limited. (x2 times)
6. Pahartali Textile and Hosiery Mills Limited.
7. Shun Shing Cement Industries Limited.
8. Etafil Accessories Limited.

  • Summary of the energy audit achievements are reported in the following documents:

Project Implementation Consultant Team’s Task Achievement Stage

Project Implementation Consultant Team’s Task Achievement Stages

Fund Disbursement

Fund Disbursement Progress – Phase 1 Project (as of December 2022)
Fund Disbursement Progress – Phase II Project (as of December 2022)

What Still Needs to be Achieved

What Needs to be Achieved